Blue Origin delayed New Glenn’s planned return to flight until January 2027, about 10 days after its previous year-end 2026 target. CEO Dave Limp told employees reconstruction at the Cape Canaveral launch pad was slowed by summer weather after a May 2026 hot-test explosion badly damaged it. The Vehicle Access Tower has been repaired and restacked, and the launch bridge restored.